CityView Portal

Permit Application Status

PRBLD201602110


You will only be able to view fees or schedule inspections if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBLD201602110
BUILDING
Closed
AQUILLA S AND BETSY S TURK
DOCK
CONSTRUCT A 500 SF - L SHAPED DOCK, A 12,000# CAPACITY BOAT LIFT AND A 20,000 # BOAT LIFT.
08/03/2016
08/29/2016
04/10/2018
10/12/2017

Locations

Permits

Permit Number: PRBLD201602110

BUILDING
Closed
08/29/2016
04/10/2018

Permit Number: PRBLD201602110

ELECTRICAL
Closed
08/29/2016
04/10/2018

Reviews

Review Type Outcome Est. Completion Date Completed
LEGACY Permit Clerk - Review Approved 08/24/2016
LEGACY Building Department/Pricing Review Approved 08/22/2016 08/23/2016
LEGACY Planning Review Approved with Conditions 08/03/2016 08/22/2016

Inspections

Inspection Outcome Requested Scheduled Date Inspected
NOC Required Received 8/18/2016 08/05/2017
Carlota de la Sierra ((305) 664-6435)   Send Email
BUILDING: AUGERS VOID/Not Required 10/12/2017
Sheila Denoncourt ((305) 664-6430)   Send Email
BUILDING: DOCK SLAB STEEL VOID/Not Required 10/12/2017
Sheila Denoncourt ((305) 664-6430)   Send Email
ELECTRICAL: FINAL Passed 10/12/2017 10/12/2017
Terri Sullivan ((305) 664-6432)   Send Email
BUILDING: DOCK FINAL Passed 10/12/2017 10/12/2017
Terri Sullivan ((305) 664-6432)   Send Email
BUILDING: OTHER VOID/Not Required 10/12/2017
Terri Sullivan ((305) 664-6432)   Send Email
BUILDING: FINAL VOID/Not Required 10/12/2017
Terri Sullivan ((305) 664-6432)   Send Email
BUILDING: GRADE BEAMS VOID/Not Required 10/12/2017
Terri Sullivan ((305) 664-6432)   Send Email
ELECTRICAL: OTHER VOID/Not Required 10/12/2017
Terri Sullivan ((305) 664-6432)   Send Email

Conditions

Condition Status Category
Physical Address Numbers Required Open
Building
Physical Address Number Required to be posted.
All docks with boat lifts, davits or similar lifting mechanisms shall provide cleats, rings, or similar features... Open
Planning
All docks with boat lifts, davits or similar lifting mechanisms shall provide cleats, rings, or similar features that can be used to tie down the vessel when it is out of the water in order to stabilize the vessel during high wind.
Lift and vessel may not exceed more than 25% of width of canal Open
Planning
Lift and vessel may not exceed more than 25% of width of canal.
When boat is attached to lift, no portion of the boat shall cross the property line Open
Planning
When boat is attached to lift, no portion of the boat shall cross the property line.
No native vegetation removal this permit Open
Planning
No native vegetation removal this permit.
Issuance of a development permit by the Village does not in any way create any right on the Resolved
Planning
Issuance of a development permit by the Village does not in any way create any right on the part of an applicant to obtain a permit from a state or federal agency and does not create any liability on the part of the Village for issuance of the permit if the applicant fails to obtain requisite approvals or fulfill the obligations imposed by a state or federal agency or undertakes actions that result in a violation of state or federal law.
The applicant or permit holder shall obtain all applicable state and federal permits prior to the start of Resolved
Planning
The applicant or permit holder shall obtain all applicable state and federal permits prior to the start of construction for the development authorized pursuant to this permit.
Miscellaneous 1 (fill in)... Open
Planning
The dock and walkway shall be located so as to avoid or minimize impacts to mangroves. Whenever feasible, piers shall incorporate light-penetrating grating on the walkway. Reflective navigation indicators shall be located every 50 feet and on both sides of the terminal platform.